Maryport Flood Defences, Maryport, Cumbria


Completed trestle structure, Maryport Harbour

Client Birse Civils Ltd / Allerdale Borough Council, Workington, Cumbria
Consultant Posford Haskoning, Newcastle
Value £800,000
Duration 40 weeks

This was Southbay Civils main contract for the year 2002 - 2003.

Construction of a variety of flood defences to Maryport.

Involving a mixture of repairs to existing structures and construction of new structures.

Works were undertaken in harsh tidal conditions on the north and south piers of Maryport Harbour, Cumbria.

1. Dismantling and reconstruction of a tidal timber trestle structure. (pictured)
2. Repair and renew concrete foundations to existing piers.
3. Construction of reinforced concrete retaining walls.
4. Concrete protective “toe” to existing piers. (pictured)
5. Concrete paving.
6. Reinforced concrete flood walls.
7. Reconstruction of a timber groyne structure.

Total volume of concrete placed by Southbay Civils was 4,150 cubic metres.

Contract completed on schedule, within budget, no accidents or incidents.



Concrete buttress constructed on existing pier to prevent undermining.


Concrete deck pour, trestle structure, Maryport Harbour.

a onebestway website